No Games Stadium To Be Ready In Time For Handover, Completion Claims Ring False


By akansha, Section CommonWealth Games 2010
Posted on Wed Jul 21, 2010 at 03:49:43 AM EST

On August 1, the agencies constructing Commonwealth Games venues are supposed to hand over the finished stadia, Games Village and other sites to the Organizing Committee, which will then start crucial overlay work to ready these sites for the event. But come August 1 and what the OC will actually get is not just unfinished competition venues like the main stadium but also uncompleted accompanying projects like landscaping, approach roads and clearing of debris.

In short, the handover will be mostly technical, with agencies like CPWD and DDA continuing to frantically work after August 1 even as the OC begins overlay work in tandem, officials admit. How the two agencies will plan their work without getting in each other's way and whether there will be time left for trials is anybody's guess.

A senior DDA official admitted, ``The finishing touches like landscaping and other work is going to continue after August 1.''

Apart from finishing construction, most venues need to tackle the mounds of debris remaining on the premises. While OC spokesperson Lalit Bhanot declined comment, sources say the fact that most of the remaining construction work is for approach roads as well as landscaping is worrying.

Apart from finishing construction, most of the Games venues also need to tackle the huge amount of debris that still remains within the premises. ``Frankly, the debris is the least of our problems, since that can be cleared out soon. But landscaping and roads within the premises are important aspects that should ideally have been completed.''

Source: Times Of India By Rumu Banerjee No Games stadium to be ready in time for handover

Click On "Full Story" For More....

   
As per the venue owner agreements with the OC, the venues are all to be handed over on August 1 with the OC remaining in-charge of the premises till October 20. The idea was to give enough time to the OC for its overlay work -- basically putting up temporary structures needed to conduct the Games.

According to Lalit Bhanot, OC spokesperson, the majority of the overlay work is expected to take place outside the actual stadium. Said Bhanot, ``From setting up tents to cabling and marking broadcast areas, all of this is part of the overlay work. Most of it will be outside the actual stadium.''

At the Village, the slow pace of work prompted the L-G on Tuesday to visit the site again, so that more manpower is deployed to finish the work. Of the 34 towers that were to be furnished by the ITDC for the Games, only two has been completed. Officials claim the rest will be done after the hand over.

The Yamuna sports complex still doesn't have a pedestrian movement plan, even though work here is pegged to be completed by July 31.

In fact, a number of venues are still to be completed both the main athletics stadium as well as the weightlifting stadium at Jawaharlal Nehru complex, the SP Mukherjee swimming pool complex, the Siri Fort and Yamuna sports complex as well as the Commonwealth Games Village. This is as per an internal report of the ministry of sports and youth affairs.

Agencies claim the work left is ``minimal''. Said a senior official, ``Only the finishing touches are left. It can be done alongside OC's overlay work.''

That's a statement which may ring false considering venues like JN's weightlifting stadium is still getting a roof or the SP Mukherjee swimming pool complex, which is still to be completed.

< Gurgaon Will Get A New Flyover At IFFCO Chowk.....

Win A Jeans Twice a Week
&
Win A Kurta 7 Days A Week

Login

Membership has its privileges. Choose a username and provide a working email - that's all it takes to join. Click below to make a new account.
Make a new account

Username:
Password:
Bangkok
BIHARSCOOP.COM
JEWELRYFRIEND.com

Who's Online? (38)

. Sanjay Sharma
. Unregistered Visitors (37)

Note: You may cloak yourself from appearing here in your Display Preferences.

Recent Comments

. How is the Dwarkadhis project in Dharuhera? (doonamit2005)

. Builders considering BUY 1 GET 1 OR 2 FREE (luckyindialucky)

. Builders considering BUY 1 GET 1 OR 2 Offer (luckyindialucky)

. Be Fair. (Hulk Hogan)

. Mr Rohtas Goyal (Nilesuffering)

. suffering continues (Nilesuffering)

. M-Tech : Fraud or Victim (susheel vats)

. Stock prices has no relation to apartment prices (Rishi)

. Hi (dkukreja)

. bubble (EquityInvestor)

Recent Member Diaries

PAYING GUEST ACCOMODATION AVAILABLE
by Freeman - November 14
62 comments


Paying Guest Accomodation for Girls in Sushant Lok
by poonam23 - November 13
38 comments


Skoda Amb 2002 VIP Number for sale
by phugatboy - November 13
5 comments


Unitech's Strategy for coming years
by malikboss - November 2
37 comments


Is there a blind home in Gurgaon?
by SGARG - October 30
8 comments


Traffic Jams on the Roads
by Pradeep - October 16
13 comments


SANTRO XING FOR SALE
by satishcmishra - October 15

Breeding nurseries of mosquitos for DLF city
by RAJKUMAR77 - October 11
1 comment


PREVENTIONS IN THE SEASON OF DENGUE
by sumandua - October 11

KLJ TOWN PLANNERS PVT LTD
by nd - October 4
28 comments



More Diaries...

Front Page

Monday September 6th
. Realty Giants To Bare It All From April (0 comments)
. At Rs 1.5 Lakh/Sqft, Borivali Property Sells For Record Price (0 comments)
. Real Estate: Invest In A State That Has An Apartment Act (0 comments)
. After CM's Decision To Call Off Five Township Projects, UP Farmers Demand Revival Of The Same (0 comments)
. Parking Woes At Gurgaon Metro Stations (1 comments)
. Marks & Spencer Drops Gurgaon Supplier (0 comments)
. National Anti-Corruption Strategy: Your Chance To Work For A Corruption Free India (0 comments)
. Rs 750cr Cover Sought By CWG Organising Committee For Common Wealth Games (0 comments)
. Northern Peripheral Road Will Redefine The Real Estate Dynamics Of Gurgaon (4 comments)

Sunday September 5th
. Full Metro Line Opens: Gurgaon To Heart Of City In 40 Minutes (0 comments)

Saturday September 4th
. Falling Prices Bring Homes Closer (0 comments)
. UP Government Scraps Yamuna Expway Township Project (0 comments)
. Hope On Property Price Dip In Noida After FAR Rise (0 comments)
. Carrefour To Open First Delhi Outlet In 2 Months (0 comments)
. 93m Slumdwellers By Next Year,Marks Increase Of 23% Since 200; Selja Assures Problem Will Be Tackled (0 comments)
. Far Raised, Noida Set To Grow Taller, Greener, More Flats Soon As Ratio Up From 2.5 To 3 (0 comments)

Friday September 3rd
. DLF May Outsource Management Of Luxury Resorts To Hilton (0 comments)
. Residential Property Prices Dip 7% In Delhi, 15% In Kolkata (0 comments)
. Traffic, Tenant Verification Top Gurgaon Cops' List (0 comments)
. The 45-km Line From Jehangirpuri To Huda City Centre Has Started (0 comments)
. PE Firms Look To Raise Funds From Market (0 comments)
. Govt To Take Up 8 New SEZ Proposals On Sept 16 (0 comments)
. Realtors, Banks Cheer As Home Loan Rebate Stays (0 comments)

Thursday September 2nd
. 'Indian Real Estate, One Of The Better Performing Markets' (0 comments)

Wednesday September 1st
. Now You Can Build 3-Story House In Noida.. (0 comments)
. Travelling From Cyber City To Maneser Will Be Jam Free... (0 comments)
. Cybercity Firms Inspire Change (0 comments)
. Towing Contractors To Pay For Damage To Vehicles (0 comments)
. Keeping Track: Traffic Police Wants GPS In Call Centre Cabs (0 comments)
. 67 Faridabad Unauthorised Colonies To Be Regularised (0 comments)

Tuesday August 31st
. Haryana Plans Overhauling Of Transport Deptt (0 comments)
. Housing Loans May Be Costlier Soon (0 comments)
. Haryana Tourism Department To Offer Discount On Food On Sept 1 (0 comments)
. Realtors Happy Over Tax Exemption On Housing Loan Interest (0 comments)
. Haryana Likely To Enhance Land Acquisition Rates (0 comments)
. Home Loans: BPLR Rates Are Rising, Shift To Base Rate (0 comments)
. PWD `Fails' To Clear Pathway, Rs 109-cr Highway Project Hits Roadblock (0 comments)
. Allot Plots To Affected Farmers, To Get Within 24 Hrs (0 comments)
. Online Employment Registration In Haryana (0 comments)
. Haryana Police Housing Corporation To Build Rs. 300 cr Police Line In Manesar, Palwal, And Mewat (0 comments)
. 6 Hospitals To Be Upgraded In Haryana (0 comments)

Monday August 30th
. Price Watch: A Weekly Comparison Of Prices Of Essential Food Commodities On Sale At Kendriya Bhandar (0 comments)
. In Spotlight: Haryana's Land Acquisition Policy (0 comments)
. DDA Work Leaves Road Full Of Potholes (0 comments)
. Haryana School Children To Get CWG Holidays Oct 8-13 (0 comments)

Sunday August 29th
. Haryana Govt Constituting Special Health Teams For CWG (0 comments)
. Available For Rent 3BR+Study In Orchid Petals, Sohna Road (0 comments)
. Buyer Can Opt Out Of Housing Project If Possession Is Delayed (0 comments)
. No Entry For Haryana Auto's In Delhi..... (0 comments)
. Delhi Transport Department Wants 'Metro Ring' On The Lines Of Ring Road... (0 comments)

Older Stories...


All trademarks and copyrights on this page are owned by their respective companies. Comments are owned by the Poster. The Rest (c) GurgaonSCOOP.com and QBTPL.
Home | Ask Questions | Computer Gupshup | Free Member Diaries | Contact Us - Sanjay @ 98 712 19911